Archived Page

This page is no longer maintained.
For up-to-date information please see the new website

Gravel Extraction in Taplow

The next phase of gravel extraction from Taplow Quarry will start soon, so the Community Liaison Group met for an update on 25th September.

Site Visit

The site has been dormant for a couple of years following the first phase of extraction. The completed area is now about 5m lower than the original land level: soil has been re-laid and a good-looking expanse of grass now covers it. The site is well drained and could easily be used as playing fields (it is flat, but not all level so more work may be needed for some uses).

The next area to be dug has been marked out and the soil was cleared in August. Topsoil and subsoil are stored in separate heaps in the worked-out part of the site. When this area is worked out, a similar area to the south of the access road will be cleared, with the soil being laid directly into the first area and re-seeded.

The gravel here forms one of the "Taplow Terraces". It is relatively clean (free of mud and clay) and has a good proportion of sand. The beds are deeper than most in the area - 5.5m on average with some areas up to 8m deep, giving more gravel from a small area of land. The gravel bed sits on a thick layer of chalk, and the water table is some 30m down at this point so the workings will remain dry.

One interesting note was that in the last ice age the glaciers came as far south as Beaconsfield, and when they melted the runoff water carved deep channels and caves in the chalk. Later rivers deposited moraine in the form of gravel beds in these depressions, leading to the land-form that we now see.

Meeting

Extraction work will begin on 9th October. Demand is currently low so the site will only operate Tuesday-Wednesday-Thursday to start with. Working hours will be 07:30 to about 16:00 There will be one digger and one water bowser on-site, with one employee to operate them. 5 lorries will be used, with each making about 10 round-trips per day to the Monkey Island Lane processing plant. Around 1000 tonnes per day will be extracted. Summerleaze believe that this phase will run for about 18 months, and yield around 230,000 tonnes.

Most of the gravel goes to customers within 5 miles of the processing plant, with small amounts travelling up to 10 miles.

Claires Court Schools have expressed interest in taking over the site for playing fields when extraction ends. Their current fields are on a yearly lease from the Licensed Victuallers Association so they feel a bit insecure.

Residents of Boundary Road were concerned about noise and dust. The worst of that should be over for now, as topsoil clearance generates far more of both than gravel extraction does. Summerleaze will install a monitoring station between the work-site and the houses so that any problems can be investigated properly.

Any problems should be reported to the Planning department at Buckinghamshire County Council.

Andrew Findlay